Update 3, July 25
Update 3, July 25

press to zoom
Update 2, July 25
Update 2, July 25

press to zoom
build-final-logo
build-final-logo

press to zoom
Update 3, July 25
Update 3, July 25

press to zoom
1/9

Aspen Lakes West Build in Blackfalds

current builds Website.png

Phase II Aspen Lakes West
5616 Vista Trail
Blackfalds, Alberta

Our build project of two duplexes is well underway at Phase II Aspen Lakes in Blackfalds. Once completed, these duplex units will be home to The Carr's, The Drake's, The Baray's, and The Gauthier-Johanneson's. 

April 2022 

On April 21 Habitat Red Deer broke ground on its 43rd, 44th, 45th, and 46th home build in Phase II at Aspen Lakes. It was a cool and windy day, but with partner families, Blackfalds town council and other community members in attendance we persevered and kicked off Habitat's newest build. 

​May 2022 

We hit the ground running in May! Official construction began at Phase II Aspen Lakes on May 9 with Marshall Construction. Parkland Geo also did our soil testing, and the site survey was completed by Snell & Oslund. At this time our foundation was poured, and our site services were completed by Atco Gas, Fortis Alberta, Shaw Cable, and Pass Electric. 

June 2022 

 

In early June framing was able to commence on June 8th with Citadel Construction. Wolf Creek Building Supplies provided the lumber packages, and Timber Wolf Truss supplied our floor systems. We also hosted our first two TeamBUILD events of the summer with Team Dow and Team Gary Moe, and Eagle Builders sent out 30 volunteers on two different Saturdays. What an amazing community we have!

July 2022 

July was a very busy month at our build site! We hosted three TeamBUILD events (Team Southern Irrigation, Team Lacombe Ford, Team MNP), and two WomenBUILD events with Team Black Press Media and a few of our partner family ladies. Our construction supervisor Nate Crowe-Swords had the teams build deck packages, and framing also continued throughout July. Additionally, Bruin's Plumbing & Heating completed the ground work at the build site by the end of July. 

August 2022 

August was a scorcher of a month with weeks upon weeks of hot weather, but this is Alberta and we know our weather can change on a dime so the show must go on! For the month of August framing continued, bringing us almost ready for the mechanical sub-trades to complete their rough-in work. 

We also hosted Team Olymel for a TeamBUILD event on August 13th, where they endured the heat and helped Nate build interior walls on the second duplex unit. Thank you, Team Olymel!

D0BB5E62-E047-4F1A-8A29-FB0EC3021E7F.jpg
F5B957EA-F67B-4DB7-B90E-B808A54C218B.jpg

September 2022 

September we saw a lull in TeamBUILD's with the summer wrapping up and everyone getting their kids back to school, but the work didn't slow down at our build!

The mechanical rough in work on the first unit was completed by Bruins Plumbing and Heating and Pass Electric, and our build is ready for all concrete work by the end of the month. Up next will be interior systems such as insulation and drywall, along with the exterior siding stone and parging. 

October will see us ramping up with TeamBUILD's again as we are entering into the interior insulation and drywall stage. We welcome Nova Chemicals and Allstate Insurance out in the first week of October, and a little later in October we will be joined by Servus Wealth Strategies and RBC Wealth Management's team, so stay tuned for that! 

 

Exterior both duplexes Sept 16.jpg
Framing 2 Sept 16.jpg

October 2022

For what we lacked in September for TeamBUILD's, we more than made up for in October! In the month of October we welcomed Team Nova on October 4 and 6th, Team Allstate Insurance on October 7, Team Servus Wealth Strategies on October 20, and then finished the month off with Team ATCO on October 25th and Team RBC Wealth Management on October 26th. We can't thank our corporate build volunteers enough!

By late October both duplex units are roughed in mechanically and electrical. The first building is insulated and ready for drywall, and the second unit has insulation loaded and ready to be put up. For the exterior work, all decks and stairs have been built and installed (thank you, volunteers!). The trades that we have had on-site have been Five Point Exteriors for siding, Joe Hey completing the interior systems, and Solera Developments will be doing the stone work. 


In November we don't anticipate alot of volunteers as the trades will still be finishing up the insulation and drywall, but are excited to have them in again once painting has started!

IMG_6245.JPEG
IMG_6223.JPEG